Dev Cycle 33
Tags:
We finished up Development Cycle 33 last week, which spans October 1st through the 19th. Here are some of the highlights for this cycle:
- Banner Updates – Several modifications to Banner were completed during this cycle including changes to the Alumni, Accounts Receivable, Financial Aid, Human Resources and Position Control modules.
- MyACU Refresh – Progress has slowed on this project as we continue to deal with loss in personnel and look to rehire for each of the open positions.
- Weaver Auditors – Over the last two weeks, a team of auditors from Weaver, LLP, have been on campus performing an audit of Information Technology’s policies and practices. A number of development tickets were completed in support of this project.
- OpenClass – Work continues as the campus prepares for the migration from Blackboard to Pearson’s OpenClass.
- Business Intelligence – Tableau was installed on the new remote desktop server, Ezra, and a number of data sources were created to give Tableau users access to needed information.
- Motorhelp – 17 Updates and bug fixes were applied to Motorhelp.
In all, 57 developer tickets were completed during this development cycle.