Teams

  • MSL – Melanie, Sara Beth & Lauren
  • HAT – Haley, Al & Tana
  • KSK – Kasi, Shannon & Kirsten
  • BLNC – Briana, Lisha, Nicole & Chad

2012 Retail Design Institute Competition

For more information specific to the RDI Competition, please go here. There are some good Q&A documents that may help with design direction.

Programming Info/Pre-Design

  1. Project Information (Design Problem, Goal & Objectives, Space Allocation
  2. Research (Location, Competition/Positioning, Consumer Habits, Trends in Retail Design, Green Design)
  3. Code Review (Complete Checklist, Document Code Sections referred to)
  4. Case Studies
  5. Inspiration
Construction Drawings
  • GN.00 – Cover w/Drawing Index (T.O.C.)
  • GN.01 – General Notes, Code Info., Abbreviations, Accessibility Notes
  • LS.XX – Life Safety Plans (first and second levels), Legends, Occupancy Schedule
  • I2XX – Dimensioned Floor Plans (first and second levels), Legends
  • I3XX – Reflected Ceiling Plans (first and second levels), Legends
  • I4XX – Finish & Furniture Plans (first and second levels), Legends, Notes, Abbreviations
  • I5XX – Interior Elevations
  • I6XX – Wall Types and Sections
  • I7XX – Millwork Details
  • I8XX – Details
  • Stair Plans and Section

Schedule & Deadline

Week 1:

  • Thurs., Feb. 16: Introduce project and design teams

Week 2:

  • Tues., Feb. 21: Precedent research and code review
  • Thurs., Feb. 23: Discuss deliverables and schedule, Team meetings

Week 3:

  • Tues., Feb. 28: Team meetings as required
  • Thurs., Mar. 1: Programming document due
Week 4
Week 5 (Spring Break)
Week 6
Week 7:
  • Tues., Mar. 27: Schematic Design due
Weeks 8 – 12
Week 13:
  • Wed., May 9: Construction Drawings due