Project Update for the week of May 10, 2010

by   |  05.24.10  |  Uncategorized

The relocation of a gas line, as well as a sanitary/sewer line, are anticipated to be completed on schedule, next week. Relocation of these two lines has gone according to schedule and without difficulty.

Almost all of the demolition will be completed by mid-week.

Excavation on the southwest side of the site is complete, and drilling for piers has begun.

Excavation has now begun on the north and east side of the site, and drilling for piers will move to those areas soon.