Project Update for August 1-20, 2010

by   |  08.19.10  |  Uncategorized

Construction is continuing on the basement walls and basement floors in select areas. Grade beams have also been installed.

Work has begun on the existing pool and surrounding pool area, beginning with reworking the drains, tile work and lighting.

Piers are still being drilled; 220 of 330 piers are now complete. Once all piers have been drilled and placed,  slab work will begin, as well as building up the structure.

The Rec. Center project is still carrying roughly a 50-day delay, which will be made up once the structure starts to go up. The time is expected to be recoverd by mid-year of 2011.