Project Update for August 21-September 21, 2010

by   |  10.08.10  |  Uncategorized

Structural work is still being done on the Student Recreation Center site.
Now, well over 230 of the 300 piers have been drilled and complete. Once all piers have been drilled and placed,  slab work will begin, as well as building up the structure.
The basement was are also all now complete, and backfilling there has begun.
In the northwest corner, grade beams have been poured, and hollow core is set to installed soon. Grade beams are also being currently poured in the southwest corner, as well as the east side.
Work on the updating the existing pool is also well underway; the new pool drains have been completely installed, and tile repair is has begun.
Electrical, mechanical and plumbing work is still continuing in the basement areas.

The Student Recreation Center project is still carrying a delay, which will be made up once the structure starts to be built up; around this time, updates on this site will be made weekly. The time is expected to be recoverd by mid-year of 2011.